{"id":3092,"date":"2026-07-03T17:09:47","date_gmt":"2026-07-03T09:09:47","guid":{"rendered":"https:\/\/panocourt.com\/?p=3092"},"modified":"2026-07-03T17:19:19","modified_gmt":"2026-07-03T09:19:19","slug":"padel-court-installation-johannesburg","status":"publish","type":"post","link":"https:\/\/panocourt.com\/th\/padel-court-installation-johannesburg\/","title":{"rendered":"Padel Court Installation Johannesburg: Foundation to Commissioning Guide (2026)"},"content":{"rendered":"<p>I have been on site through every phase of padel court installation in Johannesburg projects. I have watched the process from site preparation through commissioning, asked every technical question I could think of, and seen firsthand what separates a padel court installation that performs correctly for fifteen years from one that starts generating expensive problems in year two. This guide is the practical technical knowledge that Johannesburg padel court investors need before their installation begins.<\/p>\n<p>The padel court installation process in Johannesburg follows the same fundamental sequence as any other location \u2014 steel structure, glass panels, artificial turf, lighting. But Johannesburg&#8217;s environment creates specific requirements at each phase that a standard European or coastal South African installation specification will not fully address. Altitude, UV intensity, hail exposure, temperature cycling, and the geological conditions specific to the Highveld all interact with the installation process in ways that determine whether your court performs at specification for its full operational life or becomes a maintenance problem within a few years of opening. For the full investment context, start with the <a href=\"https:\/\/panocourt.com\/padel-court-johannesburg\/\">complete padel court Johannesburg guide<\/a>.<\/p>\n<figure class=\"wp-block-image size-large\"><img decoding=\"async\" src=\"https:\/\/panocourt.com\/wp-content\/uploads\/2026\/06\/\u5357\u975e\u573a\u5730\u56fe.jpg\" alt=\"padel court installation Johannesburg - completed PanoCourt panoramic court in South Africa\" title=\"Padel court installation completed in South Africa\" \/><figcaption>A completed PanoCourt installation in South Africa \u2014 the result of the exact installation sequence this guide documents.<\/figcaption><\/figure>\n<h2>Phase 0: Pre-Installation Preparation \u2014 What Must Be Complete Before the Crew Arrives<\/h2>\n<p>Installation day is the end of a long preparation process. If any of these elements are incomplete or incorrect, installation delays cascade into cost overruns that are far more expensive to fix than they would have been to prevent.<\/p>\n<h3>Approved Building Plans on Site<\/h3>\n<p>All construction in Johannesburg must proceed in accordance with <a href=\"https:\/\/www.joburg.org.za\/\" target=\"_blank\" rel=\"noopener\">City of Johannesburg<\/a>-approved building plans under the applicable building regulations. Approved plans must be on site and accessible to the installation crew, site supervisor, and the structural engineer conducting the required inspection at defined stages. Construction proceeding without approved plans creates legal liability and can result in a municipal stop-work order or demolition notice. This is not a formality \u2014 it is a legal requirement.<\/p>\n<h3>Concrete Slab Fully Cured to Design Strength<\/h3>\n<p>The court structure must be installed on concrete that has achieved its design compressive strength. Standard structural concrete at 25MPa minimum (30MPa preferred for Johannesburg installations subject to thermal cycling and heavy use) requires a minimum 28 days of curing before loading with the steel structure. Installing on under-cured concrete risks anchor bolt pull-out and long-term slab cracking under cyclical thermal loading. The 28-day cure is engineering science \u2014 it cannot be shortened by adding more cement or applying heat.<\/p>\n<h3>Anchor Bolt Positions Verified Against Structural Drawings<\/h3>\n<p>The pre-embedded anchor bolt positions in the slab must match the court manufacturer&#8217;s structural drawings exactly. Even a 50mm position error requires significant remediation once the steel erection has begun. Verify every anchor position against the drawings before accepting the slab from your civil contractor. This quality control check takes 30 minutes and prevents hours of expensive rework.<\/p>\n<h3>Underground Services Clearance Confirmed<\/h3>\n<p>Confirm that no underground services \u2014 water mains, sewer lines, electrical cables, telecommunications infrastructure \u2014 cross the court area or the construction zone. Contact Joburg Water, City Power, and Telkom before any excavation begins. Striking an underground service on a Johannesburg construction site is dangerous, expensive, and creates delays that can compress the entire project timeline.<\/p>\n<h3>Site Power and Access Logistics<\/h3>\n<p>The installation crew needs construction power for tools and equipment. Confirm with City Power that your supply connection is energised. Given Johannesburg&#8217;s load shedding reality, a backup generator on site is recommended to maintain installation progress through power outages. Access for glass delivery vehicles and a crane or telehandler for lifting structural members and glass panels must also be confirmed \u2014 gate widths, road restrictions, and suburban access limitations are practical issues that create real delays when discovered on installation morning rather than the week before.<\/p>\n<h2>Phase 1: Foundation Assessment and Slab Interface Check<\/h2>\n<p>Before steel erection begins, the installation crew and your structural engineer should conduct a formal inspection of the completed slab to confirm: level tolerance across the full court area is within plus or minus 3mm, all anchor bolt positions are within specification, the slab surface is clean and free of contamination that would affect base plate seating, and the drainage outlets are clear and functional.<\/p>\n<h3>Johannesburg Geology: The Risks That Affect Foundation Performance<\/h3>\n<p>The Johannesburg metropolitan area has diverse geological conditions that affect how a padel court foundation performs over time. Dolomite underlies significant parts of the region \u2014 particularly Centurion, Roodepoort, and parts of southern Johannesburg \u2014 creating sinkhole risk that requires a specialist Dolomite Risk Management Report from an accredited practitioner before any construction in designated risk zones. The City of Johannesburg maintains dolomite risk zone maps that are publicly accessible and must be consulted during the site evaluation phase.<\/p>\n<p>The black clay soils (locally called brickfield clay or expansive clay) found across parts of the Highveld expand significantly when saturated and contract when they dry out. This seasonal volume change can heave and crack a court slab over years of operation if the foundation design does not account for it. A geotechnical investigation confirming the soil profile specific to your site protects against this risk at the design stage rather than managing its consequences after the courts are operational.<\/p>\n<p>Mining activity underlies parts of Johannesburg&#8217;s southern areas. Subsidence risk from old workings is a real consideration for construction in these zones and must be assessed in the geotechnical investigation. The full foundation specification for Johannesburg padel courts \u2014 concrete strength, reinforcement, drainage design, and level tolerances \u2014 is covered in the <a href=\"https:\/\/panocourt.com\/padel-court-construction-guide-2026\/\">padel court construction phase guide<\/a>.<\/p>\n<h2>Phase 2: Steel Structure Erection<\/h2>\n<p>Steel structure erection is the fastest phase of padel court installation and the one that establishes the dimensional accuracy of everything that follows. An experienced crew can erect the main steel structure of a standard panoramic court in two to three days. The sequence and quality control at each step determine the accuracy of the finished installation.<\/p>\n<h3>Base Plate Installation and Alignment<\/h3>\n<p>Base plates are bolted to the pre-embedded anchors in the slab. Every base plate position is checked against the approved structural drawings before any bolt is torqued to final specification. Plates that do not align are corrected at this stage through shimming or minor adjustment \u2014 it is significantly easier to correct alignment before the posts are vertical than after the structure is up.<\/p>\n<h3>Vertical Post Erection and Bracing<\/h3>\n<p>Vertical posts are lifted into position \u2014 using a small telehandler or crane for heavier section members \u2014 and temporarily braced with adjustable props until the horizontal frame members are installed and the structure becomes self-stable. Each post is plumbed with a spirit level or laser before the brace is tightened. A standard panoramic court has 16 to 20 vertical posts; each one that is out of plumb by more than the permitted tolerance compromises the alignment of the glass panels installed later.<\/p>\n<h3>Horizontal Frame Members and Structural Bracing<\/h3>\n<p>Horizontal rails and diagonal bracing are installed in the sequence specified in the manufacturer&#8217;s installation manual. Diagonal bracing is not decorative \u2014 every element is calculated for a specific structural load path. Omitting, repositioning, or substituting bracing elements to simplify installation compromises the structural integrity of the court under wind loading and will fail the structural engineer&#8217;s compliance inspection.<\/p>\n<h3>Johannesburg-Specific Steel Installation Considerations<\/h3>\n<p>Two factors specific to Johannesburg require explicit attention during steel erection. First, thermal expansion gap maintenance: the Highveld&#8217;s temperature range from below zero to over 35 degrees Celsius creates significant thermal movement in steel structures across a year of operation. The manufacturer&#8217;s structural drawings specify expansion gap positions. These must be maintained during installation \u2014 over-tightening connections where gaps are specified causes the cracking, bowing, and joint distortion that becomes visible within two to three years of operation and requires expensive remediation.<\/p>\n<p>Second, coating integrity inspection: inspect every structural element before installation for chips, scratches, or damage to the hot-dip galvanised or powder-coated surface. Any damage exposes bare steel to Johannesburg&#8217;s UV and moisture environment. Surface corrosion that starts on a scratch on the day of installation becomes a structurally significant issue within five years. Repair every coating defect with a zinc-rich primer touch-up before the element is installed, not after the structure is complete.<\/p>\n<figure class=\"wp-block-image size-large\"><img decoding=\"async\" src=\"https:\/\/panocourt.com\/wp-content\/uploads\/2026\/06\/f95bd10de45d7e6a4378efd0c71168b3-scaled.png\" alt=\"padel court installation team welding steel structure at PanoCourt factory\" title=\"Steel structure fabrication for padel court installation\" \/><\/p>\n<figcaption>Steel frame quality is decided at the factory: certified welding and hot-dip galvanising per EN ISO 1461.<\/figcaption>\n<\/figure>\n<h2>Phase 3: Glass Panel Installation<\/h2>\n<p>Glass installation is the most technically demanding phase of padel court construction. Panels are heavy \u2014 a standard 10mm tempered glass panel measuring 3 metres by 1 metre weighs approximately 75 kilograms; larger panels proportionally more \u2014 and must be handled exclusively with specialist vacuum lifting equipment. Dropping or edge-striking a panel destroys it and creates a replacement order, a delivery lead time, and a significant unplanned cost.<\/p>\n<h3>The Johannesburg Hail Specification Decision<\/h3>\n<p>Before glass installation begins, confirm the specification for your site. For outdoor and semi-exposed Johannesburg courts, laminated safety glass is the appropriate specification. Laminated glass consists of two layers of fully tempered glass bonded with a polyvinyl butyral interlayer. If a panel is struck and cracked by hail, the interlayer holds the pieces together \u2014 no glass scatter on the court surface, no immediate safety risk, and a managed repair rather than an emergency court closure. Standard fully tempered glass, if cracked by a hail impact, breaks into fragments that make the court immediately unplayable and unsafe.<\/p>\n<p>The additional cost of laminated glass over standard tempered glass per panel is R500 to R1,500 depending on panel size. For an outdoor Johannesburg court with 20 to 24 glass panels, the specification upgrade adds R10,000 to R36,000. Given the cost and disruption of emergency glass replacement after a Highveld hailstorm \u2014 the direct cost of replacement panels, the lost revenue during closure, and the reputational impact on your members \u2014 this specification upgrade is a sound investment.<\/p>\n<h3>Glazing Channel Alignment: The Installation Detail That Causes Spontaneous Glass Failure<\/h3>\n<p>Glass panels locate in aluminium or stainless-steel glazing channels at the base and mid-height of the court perimeter. These channels must be perfectly aligned in plane before any panels are installed. A glazing channel that is even 2 to 3mm out of plane across its length creates a point stress concentration at the glass panel edge where it contacts the channel at the high point. This stress concentration causes spontaneous panel cracking \u2014 sometimes weeks or months after installation \u2014 that cannot be attributed to any specific impact event and is therefore not covered under glass manufacturing warranty. The installation crew must use a laser or straight-edge to confirm channel alignment before the first panel is installed.<\/p>\n<h2>Phase 4: Artificial Turf and Sand Infill Installation<\/h2>\n<p>The playing surface is what every player interacts with on every shot, every session, every day of your court&#8217;s operational life. Turf installation quality directly affects court playability, player satisfaction, and the interval before the surface requires replacement.<\/p>\n<h3>Turf Roll-Out Sequence and Seam Bonding<\/h3>\n<p>Turf is rolled out in the manufacturer-specified direction \u2014 pile direction is consistent within a roll and must be consistent across the full court area to produce uniform playing characteristics. Any seams are bonded with specialist adhesive and reinforced with seam tape running the full seam length. Seams in a correctly installed padel court are invisible and structurally continuous \u2014 a player&#8217;s foot crossing a seam should detect no step, gap, or texture change. Visible or elevated seams are an installation defect that must be corrected before handover is accepted.<\/p>\n<h3>Infill Application: The Technical Detail That Determines Playing Quality<\/h3>\n<p>Incorrect infill application is the most common turf installation defect in padel courts across the industry. Under-infilling leaves turf pile exposed and unstable \u2014 ball behaviour is inconsistent with standard padel, the surface wears and degrades prematurely, and players can feel the instability in their footwork. Over-infilling compacts the pile, creates a hard low-friction surface, and changes the ball trajectory in ways that are immediately noticeable to any player who has played on a correctly specified court.<\/p>\n<p>The correct infill depth for standard padel turf with 10 to 12mm pile height is 7 to 9mm of kiln-dried silica sand. Measure this at a minimum of six points across the court area after application using a depth gauge, and document the readings in the handover report. Do not accept the installation contractor&#8217;s verbal assurance that the infill is correct \u2014 measure it.<\/p>\n<h3>Johannesburg UV Specification for Artificial Turf<\/h3>\n<p>Johannesburg&#8217;s altitude UV intensity requires turf with UV stabilisers incorporated into the fibre at manufacture through the co-extrusion process \u2014 not applied as a surface coating after production. Request the UV resistance test certificate compliant with ISO 105-B02 for the specific turf being installed, and confirm the classification grade. Grade 4 is the minimum for any Johannesburg installation; Grade 5 is strongly preferred for fully exposed outdoor courts. The complete materials specification reference, including all UV standards and performance criteria for South African conditions, is in the <a href=\"https:\/\/panocourt.com\/padel-court-materials-specifications-guide-2026\/\">\u0e04\u0e39\u0e48\u0e21\u0e37\u0e2d\u0e27\u0e31\u0e2a\u0e14\u0e38\u0e41\u0e25\u0e30\u0e02\u0e49\u0e2d\u0e01\u0e33\u0e2b\u0e19\u0e14\u0e17\u0e32\u0e07\u0e40\u0e17\u0e04\u0e19\u0e34\u0e04\u0e02\u0e2d\u0e07\u0e2a\u0e19\u0e32\u0e21\u0e1b\u0e32\u0e14\u0e40\u0e14\u0e25<\/a>.<\/p>\n<h2>Phase 5: LED Lighting Installation<\/h2>\n<p>Professional padel requires well-distributed, consistent lighting. The minimum specification for a commercial Johannesburg padel court is 300 lux maintained illuminance at playing height with a uniformity ratio of 0.7 or better across the full court area. Tournament-capable facilities targeting professional and competitive play should specify 400 lux with 0.75 uniformity minimum.<\/p>\n<h3>Load Shedding Backup Power: Non-Negotiable for Johannesburg Operations<\/h3>\n<p>Johannesburg&#8217;s load shedding is a permanent operational reality. Evening court sessions from 5pm to 10pm \u2014 the highest-revenue window for any commercial padel facility \u2014 overlap directly with the Stage 2 to Stage 4 load shedding schedules that are now a routine part of the City of Johannesburg&#8217;s operating environment. A padel facility that cannot maintain lighting during load shedding loses its highest-value sessions to darkness.<\/p>\n<p>The most practical backup power solution for a Johannesburg padel facility is a lithium iron phosphate battery storage system with an inverter sized for the full court lighting load, sized to cover a standard 2 to 3-hour load shedding window. A four-court facility at full lighting load draws approximately 20 to 30 kilowatts. A system sized for 2.5 hours of operation requires 50 to 75 kilowatt-hours of battery storage. Total system cost: R200,000 to R400,000 depending on capacity and specification. This investment protects R60,000 to R100,000 per month in prime-time court revenue from interruption.<\/p>\n<h2>Phase 6: Commissioning, Snagging, and Formal Handover<\/h2>\n<p>Commissioning is not a ceremony \u2014 it is the contractual moment at which defects must be identified and recorded. The contractor&#8217;s obligation to remedy defects is strongest at handover and diminishes over time. A formal, documented snagging process is the investor&#8217;s most important quality control tool.<\/p>\n<h3>Complete Commissioning Checklist for Johannesburg Padel Courts<\/h3>\n<p>Steel structure: all bolted connections torqued to the manufacturer&#8217;s specified values. No visible coating damage, rust staining, or surface defects on any structural element. Expansion gaps maintained at designed positions \u2014 not blocked or filled by over-tightening. Base plates seated correctly with no visible gaps between plate and slab surface.<\/p>\n<p>Glass panels: all panels inspected in daylight for chips, cracks, edge damage, or surface scratches. Panel alignment confirmed \u2014 no visible step, gap, or misalignment at any joint position. Glazing channels free of trapped debris. All panel fixing clips and gaskets present and correctly seated.<\/p>\n<p>Artificial turf: infill depth measured and documented at minimum six points per court. Seam lines straight, flat, and adhesive-bonded completely across the full seam length. Perimeter edges cleanly finished at the glass base channel with no lifted or fraying edges. No high or low spots detectable by walking the full court surface.<\/p>\n<p>Lighting: lux levels measured with a calibrated lux meter and documented at minimum four points per court. All fixtures operating. Uniformity ratio confirmed within specification. Backup power switchover tested through a complete simulated outage cycle with load applied. Controls system \u2014 timers, manual switches, remote management \u2014 functioning correctly.<\/p>\n<p>Documentation: as-built drawings reflecting actual installation, manufacturer&#8217;s warranty certificate, structural engineer&#8217;s compliance certificate in terms of the approved building plans, and electrical compliance certificate (CoC) signed by a registered electrician.<\/p>\n<p>Do not accept handover until all snagging items are either resolved or documented in a written remediation schedule agreed with the contractor and signed by both parties. Accepting handover with undocumented open defects transfers responsibility to the investor.<\/p>\n<h2>Frequently Asked Questions: Padel Court Installation in Johannesburg<\/h2>\n\n<div id=\"rank-math-faq\" class=\"rank-math-block wp-block-rank-math-faq-block\">\n<div class=\"rank-math-list\">\n<\/div>\n<\/div>\n\n<h2>Get Full Technical Support for Your Padel Court Installation in Johannesburg<\/h2>\n<p>A padel court that is correctly specified for Johannesburg&#8217;s environment, properly installed, and professionally commissioned will operate for fifteen or more years with predictable maintenance costs and consistent playing quality. A court that is rushed, inadequately specified for the Highveld&#8217;s UV, hail, and temperature conditions, or installed without proper quality control will generate maintenance costs and player complaints within two to three years of opening.<\/p>\n<p>PanoCourt provides complete installation documentation packages for every project: structural drawings, material certifications, installation manuals, and direct access to our engineering team for technical questions during construction. For Johannesburg projects, we work directly with your local ECSA-registered structural engineer to ensure all documentation meets City of Johannesburg building plan requirements and reflects the environmental specifications appropriate for the Highveld.<\/p>\n<p>For the complete project planning framework \u2014 from site selection through opening \u2014 see the guide on <a href=\"https:\/\/panocourt.com\/build-padel-club-johannesburg\/\">how to build a padel club in Johannesburg<\/a>. For court sourcing due diligence, see the <a href=\"https:\/\/panocourt.com\/padel-court-manufacturer-johannesburg\/\">padel court manufacturer guide for Johannesburg<\/a>. For the broader South Africa investment context, including cost benchmarks and market analysis, see our guide on <a href=\"https:\/\/panocourt.com\/build-padel-court-cost-in-south-africa-2026\/\">padel court costs in South Africa<\/a>.<\/p>\n<p><strong>Contact the PanoCourt project team via <a href=\"https:\/\/panocourt.com\/contact\/\">panocourt.com\/contact<\/a> to discuss the technical requirements of your Johannesburg padel court installation.<\/strong> We review your site conditions, confirm specifications appropriate for Johannesburg&#8217;s environment, and provide an engineering package that gives your installation the right foundation from day one.<\/p>","protected":false},"excerpt":{"rendered":"<p>Full technical padel court installation guide for Johannesburg \u2014 Highveld foundation specs, hail-rated glass, UV-stable turf, load-shedding LED strategy, steel erection, and the complete commissioning checklist.<\/p>","protected":false},"author":1,"featured_media":2977,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"site-sidebar-layout":"default","site-content-layout":"","ast-site-content-layout":"default","site-content-style":"default","site-sidebar-style":"default","ast-global-header-display":"","ast-banner-title-visibility":"","ast-main-header-display":"","ast-hfb-above-header-display":"","ast-hfb-below-header-display":"","ast-hfb-mobile-header-display":"","site-post-title":"","ast-breadcrumbs-content":"","ast-featured-img":"","footer-sml-layout":"","ast-disable-related-posts":"","theme-transparent-header-meta":"","adv-header-id-meta":"","stick-header-meta":"","header-above-stick-meta":"","header-main-stick-meta":"","header-below-stick-meta":"","astra-migrate-meta-layouts":"default","ast-page-background-enabled":"default","ast-page-background-meta":{"desktop":{"background-color":"var(--ast-global-color-4)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"ast-content-background-meta":{"desktop":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"footnotes":""},"categories":[44],"tags":[],"class_list":["post-3092","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-panoramic"],"_links":{"self":[{"href":"https:\/\/panocourt.com\/th\/wp-json\/wp\/v2\/posts\/3092","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/panocourt.com\/th\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/panocourt.com\/th\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/panocourt.com\/th\/wp-json\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/panocourt.com\/th\/wp-json\/wp\/v2\/comments?post=3092"}],"version-history":[{"count":3,"href":"https:\/\/panocourt.com\/th\/wp-json\/wp\/v2\/posts\/3092\/revisions"}],"predecessor-version":[{"id":3103,"href":"https:\/\/panocourt.com\/th\/wp-json\/wp\/v2\/posts\/3092\/revisions\/3103"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/panocourt.com\/th\/wp-json\/wp\/v2\/media\/2977"}],"wp:attachment":[{"href":"https:\/\/panocourt.com\/th\/wp-json\/wp\/v2\/media?parent=3092"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/panocourt.com\/th\/wp-json\/wp\/v2\/categories?post=3092"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/panocourt.com\/th\/wp-json\/wp\/v2\/tags?post=3092"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}