From concrete foundation to first serve: the complete construction process, site requirements and real installation costs — based on the engineering drawings we ship with every PanoCourt court. A trained crew of 4 installs one court in 3–5 days.
THE BIG PICTURE
What Does Padel Court Construction Involve?
Padel court construction has two distinct phases. Construction covers the civil works — an engineer-designed concrete foundation, drainage and pre-buried electrical cabling, delivered by your local contractor. Installation is the assembly of the court structure itself: steel frame, mesh, lighting, tempered glass and net.
Every PanoCourt court is a fully bolted system — no on-site welding — so a local steel or fencing crew can complete the installation using our drawings and remote support.
- Overall footprint 20.47 × 10.47 m (flange-plate edge) for a standard 20 × 10 m court
- Structure weight approx. 3–4 tonnes of steel and 12 mm tempered glass
- 100% bolted M8/M10 connections — standard tools only, no site welding
- Complete installation drawings, fastener maps and labelled packing included
SEE THE PROCESS
Watch a Padel Court Installation From Start to Finish
Replace this placeholder with your factory or on-site installation video.
BEFORE THE CONTAINER ARRIVES
What Site Preparation Is Required?
Installation can only begin once the foundation, drainage and cabling are complete. This is the pre-installation checklist we send every client:
- Foundation: perimeter ring beam (~30×30 to 40×40 cm) or reinforced slab 15–25 cm, min. 21 × 11 m — engineer-designed
- Surface tolerance: ±6 mm under a 3 m straightedge
- Clear height: ≥6 m over the whole court; 8 m over the net line for competition or canopy
- Electrical: pre-buried cable to each light pole position, conduit ≥450 mm deep
- Drainage: porous build-up or 0.5–1% fall with perimeter drains (outdoor)
- Access: forklift or crane access for a 40' container unload
Foundation, drainage and electrical design must be signed off by a licensed local engineer. PanoCourt supplies base-plate layouts, anchor positions, structure weights and the maximum design windspeed as engineering input.
STEP BY STEP
How Is a Padel Court Installed?
The exact 8-stage sequence from the installation drawings and manual shipped with every court.
01 · Site Layout & Marking
Mark the 20.47 × 10.47 m footprint with corner lines and centre line on the finished slab.
02 · Unpacking & Sub-Assembly
Label every component, then pre-assemble the 10 m and 20 m crossbeam groups on the ground.
03 · Main Frame Erection
Corner posts, light poles, crossbeams, mesh frames and doors — all M10 bolted connections.
04 · Squaring & Anchoring
Align and plumb the full frame, then fix expansion anchors through the flange plates into the slab.
05 · Upper Mesh & Lamp Arms
Mount luminaires and route cables through the poles to the pre-buried underground supply.
06 · Tempered Glass
Rubber gaskets top and bottom, glass on the inside face — glass never touches bare steel.
07 · Net & Net Posts
Tension the net to 905 ± 5 mm at the ends and 865 ± 5 mm at the centre.
08 · Electrical & Commissioning
Sub-breaker per court, RCD for multi-court sites, all joints sealed in UV-resistant conduit.
Two safety rules from our manual: tempered glass must never contact bare steel — always gasket or foam-tape the joint — and every electrical connection must be fully enclosed and weatherproofed.
PLANNING YOUR OPENING
How Long Does It Take?
One court takes an experienced crew of 4 around 3 à 5 jours after the foundation has cured. A first-time local crew should allow 5–7 days with our remote video support.
Typical end-to-end timeline: 25–30 days production at our factory, plus sea freight to your port, plus groundworks (which run in parallel with production and shipping), then installation.
BUDGET, HONESTLY
Combien coûte la construction d'un Padel Court ?
Installation labour is a small share of the total budget — the court structure and the civil works are the two big items. Reference ranges for a single panoramic court (confirm with an itemised quotation for your country):
| Cost Item | Typical Range (USD) | Remarques |
|---|---|---|
| Court structure (factory-direct, ex-works) | $10,000–18,000 | Panoramic vs classic; glass & steel spec |
| Sea freight (1×40’HQ, 1–3 courts) | $2,000–5,000 | Destination dependent |
| Groundworks & foundation | $8,000–25,000 | Local contractor; site conditions govern |
| Installation labour (local crew, 3–5 days) | $3,000–8,000 | Or your own crew with our drawings |
| Lighting electrical connection | $1,000–3,000 | Local electrician |
In the UK and Western Europe, a local turnkey builder typically prices the same scope significantly higher. Buying factory-direct from a China padel court manufacturer and installing with a local crew keeps the structure cost transparent — you pay contractor rates only for the work that genuinely has to happen on site.
NO LOCAL DEALER? NO PROBLEM
Can a Local Crew Install It?
Yes. Because the system is fully bolted and every component ships labelled against the drawings, clients worldwide install PanoCourt courts with local steel, fencing or sports-surface contractors — guided by our installation manual and live remote video support.
We recommend professional handling for two stages only: lifting the tempered glass panels, and the final electrical connection by a licensed electrician.
- Numbered components matched to the drawings
- Fastener map: every bolt size, connection by connection
- Remote video support during installation
- 5-year product warranty and CE documentation
BUILT IN OUR FACTORY, PROVEN ON YOUR SITE
What Does PanoCourt Provide?
Hot-dip galvanised steel to EN ISO 1461 with 80–100 µm premium powder coating, laser-cut and robot-welded in our factory. 12 mm tempered polished-edge glass, one-piece galvanised mesh and concealed stainless hardware — the same standard as premium European brands, without the brand markup.
- Complete installation drawings and manuals (EN)
- Base-plate and anchor layouts for your engineer
- Container-optimised, labelled export packing
- Maximum design windspeed stated for local wind calculations
- Anti-glare flicker-free LED lighting packages (300–500 lux)
ANSWERS BEFORE YOU ASK
Padel Court Construction FAQ
A realistic all-in budget for one court is roughly $25,000–55,000 USD: $10,000–18,000 for a factory-direct structure, $8,000–25,000 for engineer-designed groundworks, plus freight, installation labour and electrical connection. Site conditions and country labour rates drive most of the variance.
An experienced crew of 4 installs one court in 3–5 days once the foundation is ready. A first-time local crew should allow 5–7 days with our remote support. Factory production takes 25–30 days, and groundworks can run in parallel with production and shipping.
Either a perimeter reinforced ring beam (typically 30×30 to 40×40 cm) or a reinforced slab of 15–25 cm, minimum 21 × 11 m, designed by a licensed local engineer using your ground investigation and local wind loads. Surface tolerance must be ±6 mm under a 3 m straightedge.
Yes. The system is fully bolted with labelled components, complete drawings and a fastener-by-fastener manual. Local steel or fencing crews install our courts worldwide, backed by remote video support. Only glass lifting and the electrical connection call for specialist trades.
Construction is the civil works — foundation, drainage and pre-buried cabling — delivered by your local contractor to your engineer’s design. Installation is the assembly of the court structure itself. PanoCourt supplies everything for installation and the technical data your engineer needs for construction.
Yes. Every court ships with English installation drawings, a step-by-step manual, a fastener map covering every connection (M8×30 to M10×75), base-plate and anchor layouts, structure weights and the maximum design windspeed of the enclosure.
UK turnkey pricing is typically well above the structure cost alone, because planning, groundworks and labour are priced at local rates. Buying factory-direct and installing with a UK groundworks or fencing contractor usually reduces the total materially — ask us for a UK-itemised quotation.
Usually yes for outdoor courts: the 3–4 m walls and 6 m lighting columns normally require planning or zoning consent, and noise or lighting assessments may apply if homes are within about 50 m. Consent is the site owner’s responsibility — our Construction Requirements Guide covers what to prepare.
Ready to Build Your Padel Court?
Send us your site dimensions and country — we’ll reply with an itemised quotation, the installation manual and the construction requirements guide within 24 hours.